5 Q3F2004
volumes. The contribution to operating profit from Agnew was A$12 million (R61 million, US$9 million) compared with A$13 million (R61 million, US$9 million) last quarter. Capital expenditure was the same as last quarter at A$7 million (R30 million, US$5 million) as exploration and development of the underground operations at Waroonga continued.
Agnew performed above expectations once again and it is unlikely that this level of production and profitability can be maintained. As a result of the anticipated closure during the June quarter of the Crusader/Deliverer underground operation, production in the next quarter is expected to be some 10 to 20 per cent lower than the last two quarters, with a concomitant effect on margins.
C a p i t a l
a n d d e v e l o p m e n t
p r o j e c t s
ST IVES EXPANSION PROJECT
During the quarter construction of the new 4.5 million ton per annum mill CIP process plant at St Ives made good progress, following site mobilisation at the end of the December quarter. In the March quarter, site levelling, construction of the ROM pad and casting of the SAG mill and crusher foundations were well advanced, while the SAG mill and ancillary equipment was delivered to site.
By quarter end some 75 per cent of engineering works had been completed while commitments in respect of 50 per cent of the total capital expenditure had been made. The project remains on track for commissioning in the December 2004 quarter at a total cost of A$125 million.
TARKWA EXPANSION PROJECT
CIL Process Plant
The new 4.2 million ton per annum mill project advanced satisfactorily during the quarter and remains on track for commissioning in the quarter ended December 2004. All major site civil and concrete work has been completed with delivery and erection of steel work in full swing, while construction of the tailings dam continued. The fabrication of the mill, which has been on the critical path, was completed on schedule and the mill is currently being shipped to Ghana.
Noting that contingency in the budget has been largely exhausted, the project remains within the US$85 million budgeted, save for possible currency exposure on the A$ and ZAR, representing a possible US$5 million overrun, which will depend on currency moves over the next few months.
Conversion to owner mining
The first deliveries of the new mining fleet were made to Tarkwa during the quarter. By quarter end nine of the eventual twenty four 785C haul trucks had been delivered. Various graders and dozers have been delivered, commissioned and are already in service. During the coming quarter the remainder of the haul trucks and six of the ultimate eight excavators will be delivered.
Screening and recruitment of operators and technical staff, sourced primarily from the current contract workforce, has commenced, while finalisation of the majority of the consumable supply contracts is underway.
It is anticipated that the build up of the operations with the new fleet will occur in the first quarter of F2005 and that by the end of that period the overlap with the contract mining operator will cease.
ARCTIC PLATINUM PROJECT
Activity at APP continued to focus on the two large tonnage open pittable deposits at Suhanko, namely Kontijarvi and Ahmavaara. During the March 2004 quarter exploration focused on detailed in-fill drilling at the two deposits, with particular emphasis on grade control drilling in the areas targeted for the bulk samples.
Towards the end of the quarter blast hole drilling and sampling at Kontijarvi and overburden stripping in the trial mine area at Ahmavaara were completed. A bulk sample of 5,300 tons will be mined from the two deposits during the fourth quarter and processing at the pilot plant will commence. The pilot plant is intended to verify process parameters at this scale and to produce concentrate for downstream processing testwork. The trial mine, pilot scale concentrator campaign and the subsequent downstream treatment testwork is the critical path to completion of the feasibility study on this project. It is planned to reach an investment decision by the end of this calendar year.
DAMANG EXPANSION PROJECT
During the March quarter, a dedicated project team was mobilised to evaluate the various options for the Damang operation arising from the exploration programmes undertaken through to the end of the December 2003 quarter. These exploration programmes, which are largely completed, have assessed both conglomerate as well as hydrothermal styles of mineralisation on the Damang lease.
The project team is now evaluating options that include exploiting new sources of high grade hydrothermal mineralisation at Rex and Amoanda as well as a further cut back on the Damang pit, along with incremental sources of soft low
grade feed ores from Tomento and the Lima area. These options are focussed on near term production, while longer term options of developing an underground mine below the Damang pit and at the Abosso Deeps area between Tarkwa and Damang, are also being examined.
The Project team is expected to complete its work by the end of the June 2004 quarter.
E x p l o r a t i o n a n d C o r p o r a t e
D e v e l o p m e n t
CERRO CORONA IN PERU
During the last quarter, we announced the conclusion of a transaction to acquire the Cerro Corona gold and copper development project located in northern Peru.
During this quarter the Company successfully completed the first condition to closing of the acquisition, that is the completion of due diligence. The transaction remains subject to completion of the acquisition of all surface rights required to develop the project and successful permitting. During the quarter good progress was made with the former aspect while a full time project team has been established in Peru to advance all elements of the project development, including the required permitting, which is expected to be completed in the first half of the 2005 calendar year.
FURTHER CHINA VENTURES
Gold Fields further emphasised the importance of the China region by establishing a regional representative office in Beijing during the quarter. Dr. Guocheng Pan, who has consulted extensively for Gold Fields over the past five years, is managing this office. This office will be responsible for overseeing the exploration joint ventures with Sino Mining in the Shandong province and with Fujian Zijin Mining Industry ("Zijin") in the Fujian province. The Sino Gold Fields Joint Venture ("SGF") is an exploration alliance and project joint venture agreement with Shandong provincial Bureau of Geo-Mineral Exploration and Development. The co-operative joint venture is held 70 per cent by SGF of which Gold Fields has a 50 per cent share. The joint venture with Zijin, of which Gold Fields share 60 per cent, is to explore and develop gold properties in China's Fujian province. We are currently active in several other regions of China and it is hoped that Dr. Pan's extensive contacts in the country will produce results during the coming months.
OTHER PROJECTS
Gold Fields has been very active during the quarter on its extensive inventory of exploration projects.
Drilling was completed on the Tanaso, Mampehia and Bomaa prospects within our 100 per cent owned Bibiani project in Ghana. Over the last two years Gold Fields has discovered extensive surface indications on this project that is immediately adjacent to Newmont's Ahafo project. Based upon results seen to date, it is hoped an initial resource statement at Mampehia will be presented during the first quarter of F2005. Elsewhere in Africa, a third phase of drilling was approved and is nearing completion at the Essakane project in Burkina Faso. This joint venture project would allow Gold Fields to earn up to a 60 per cent interest from Orezone Resources.
In South America, drill programmes were completed at the Cañicapa prospect in Ecuador as part of the Condor joint venture with IAMGold. Drilling was also completed at the Incapacha prospect that is a part of the Puquio joint venture with Buenaventura.
In North America, mobilisation of a new winter camp and supplies has been completed at the Committee Bay joint venture in Nunavut. A major drill programme will be completed over the next two quarters on this attractive gold prospect.
C o r p o r a t e m a t t e r s
BLACK ECONOMIC EMPOWERMENT TRANSACTION
On 8 March 2004, shareholders of both Gold Fields Limited ("Gold Fields") and Mvelaphanda Resources Limited ("Mvela Resources") voted decisively in favour of all shareholder resolutions necessary to implement the transaction in terms of which Mvelaphanda Gold (Proprietary) Limited ("Mvela Gold"), a wholly-owned subsidiary of Mvela Resources, will acquire a 15 per cent beneficial interest in the South African gold mining assets of Gold Fields, including the world-class Beatrix, Driefontein and Kloof mines for a cash consideration of R4,139 million. All conditions precedent to the transaction were fulfilled following the completion by Mvela Resources of a domestic and international private placement on 15 March 2004. Following completion of the private placement Mvela Gold advanced a loan of R4,139 million ("the GFI-SA Loan") to GFI Mining South Africa (Proprietary) Limited ("GFI-SA"), a wholly owned subsidiary of Gold Fields, on 17 March 2004. This loan was financed by way of commercial bank debt of approximately R1,349 million, mezzanine finance of R1,100 million (which includes R200 million from Gold Fields) and the balance of approximately R1,690 million raised by the Mvela Resources private placement, (which